As part of the continuing development of London Gateway Port, the Berth 3 container yard interchanges and associated pavements, services and infrastructure were constructed in 2015/2016.
The scope of works undertaken by CGR for this project included:
- Detailed design of earthworks, heavy duty pavements, general pavements, ASC rails and associated foundations
- Detailed design of drainage and services
- Head office support
- Site supervisions
- Detailed design of electrical systems for the ASC's reefers and lighting